# Section 20 major works consultancy in Greenwich

Technical support for freeholders, RMC and RTM directors and managing agents planning major works to residential blocks, from condition evidence and specification to tender comparison and, where separately appointed, contract administration. Leaseholders who have received a notice can ask for a separately scoped technical review.

### Who appoints HCS

HCS acts for the client named in the written appointment. For major works this is usually the landlord or freeholder, a resident management company (RMC), a right to manage (RTM) company or the managing agent acting with their authority. Leaseholders who pay for the works through the service charge are not automatically HCS’s clients, and HCS does not represent them unless they appoint HCS separately.

Before accepting an instruction we check the building, the parties and any existing appointment. HCS will not act against an existing landlord or managing-agent client on the same matter, and does not act for both sides of a disagreement about the same works.

### For boards, freeholders and managing agents planning works

Commission the work in stages and start from the point you have reached. Each stage has its own written scope and fee, agreed before instruction, so you do not have to buy the whole programme at the outset.

- Condition evidence and scope. Review the surveys, maintenance records and proposed works you hold, inspect the agreed elements and set out a technical scope or recommendations for the next stage.
- Specification and tender. Prepare a specification or schedule of works that every contractor prices on the same basis, run the tender and compare the returns technically and commercially.
- Contract administration. If separately appointed, administer the building contract you choose: inspections at agreed intervals, instructions, valuations, completion and the defects period.
Already have a specification, tenders or a contractor? We can review what exists, for example whether the tenders priced the same scope and what each excludes or leaves provisional, without repeating earlier stages. Tell us which documents have already been issued to leaseholders.

Send a board or agent brief

### If you have received a Section 20 notice

A leaseholder, a group of leaseholders or a residents’ association can ask for a separately scoped technical review. Depending on the documents available, it can look at:

- the proposed scope and the reasons given for it;
- the surveys or condition evidence the proposal relies on;
- whether the specification describes the work clearly enough to price;
- whether the estimates were priced on a comparable basis, including exclusions, provisional sums and access assumptions; and
- technical questions to put to the landlord or managing agent during the consultation.
Questions about the lease, whether a notice is valid, tribunal strategy and whether you have to pay may need a solicitor or other legal adviser. A technical review does not by itself stop the works, cancel a demand or reduce a bill.

Tell us who the landlord and managing agent are and any response deadline stated in the notice before you send documents. We check for conflicts first: if HCS already acts for the landlord or agent on the same building, we cannot act for you on that matter. We confirm whether we can help, and by when, only after checking the deadline; an enquiry does not reserve an appointment.

Ask about a technical review

### Major works context in Greenwich

These documentary sources describe parts of Greenwich at their publication dates. Use them to frame questions about the actual building; they do not establish its condition, the leases, the consultation route or who must pay.

The council's West Greenwich appraisal says Crooms Hill begins with a substantial early Georgian terrace of 1721 set back from the road behind gardens, and credits much of the street's appeal to its topography, winding up the side of Greenwich Park to Blackheath. It describes Hyde Vale as a sequence of eighteenth and nineteenth century villas and town houses that wind up the escarpment.

##### Scaffold, rear access and neighbouring land

Terraces, mews and rear yards can make scaffold and deliveries harder to plan. Ask each tenderer to state the access method priced and say whether a route depends on a neighbour, a highway licence or garden access; different access assumptions make estimates hard to compare.

##### Where most local buildings are houses

The documentary sources here mainly describe houses. Section 20 consultation concerns service charges payable under leases, so a brief usually relates to a converted house, a purpose-built block or flats above shops. Confirm the building type, how many leaseholders contribute and how the leases share the cost.

Local sources and research limits

- [Royal Borough of Greenwich: West Greenwich Conservation Area Appraisal](https://www.royalgreenwich.gov.uk/sites/default/files/2025-07/West_Greenwich_Conservation_Area_Appraisal.pdf)
- [Royal Borough of Greenwich: Ashburnham Triangle Conservation Area Character Appraisal, December 2008](https://www.royalgreenwich.gov.uk/sites/default/files/2025-07/Ashburnham_Triangle_CAA_adopted_Dec_2008%20%281%29_0.pdf)
- [Royal Borough of Greenwich: Greenwich Park Conservation Area Appraisal, 2010](https://www.royalgreenwich.gov.uk/sites/default/files/2025-07/Greenwich_Park_Conservation_Area_Appraisal_2010.pdf)
- [Royal Borough of Greenwich: Greenwich and Blackheath conservation areas management guidance, 2010](https://www.royalgreenwich.gov.uk/sites/default/files/2025-07/Greenwich_and_Blackheath_conservation_areas_management_guidance_2010.pdf)
- [Royal Borough of Greenwich: Maps and adopted character appraisals](https://www.royalgreenwich.gov.uk/planning-and-building-control/conservation-and-listed-buildings/maps-and-adopted-character)
- [Royal Borough of Greenwich: Works to trees](https://www.royalgreenwich.gov.uk/planning-and-building-control/planning-permission-and-enforcement/works-trees)
The descriptions are retained from maintained, attributed local research reused on 16 November 2026. They are documentary context, not a current inspection of any building.

### What each stage produces

Initial assessment: a review of the surveys, records and proposed works, inspection of the agreed accessible elements (or an agreed desktop review), the evidence gaps, repair options, access issues and specialist input, and a written technical scope or recommendations for the next stage.

Specification and tender: one consistent scope for every contractor to price, a record of tender queries, exclusions, provisional items and access assumptions, a reasoned comparison with a recommendation, and technical information for the landlord’s consultation documents.

Delivery support, if separately appointed: the contract-administration duties under the chosen contract, with an agreed inspection frequency, instructions, variation records, payment assessments, completion and the defects period. It is not continuous supervision and does not certify concealed work or prevent every variation.

Missing documents, newly found defects or changed proposals can change the scope; any change to the scope and fee is agreed in writing first. See each stage’s outputs in full.

### How consultation fits the technical work

The landlord or managing agent must identify the consultation route. Ordinary qualifying works without a public-notice requirement follow [Schedule 4, Part 2](https://www.legislation.gov.uk/uksi/2003/1987/schedule/4/part/2); works needing public notice, proposed long-term agreements and works under an existing agreement follow different schedules, and an uncertain route needs advice before the first notice.

On the ordinary route, the landlord or agent issues a notice of intention with a 30-day period for observations and nominations, obtains estimates, then issues a statement of at least two estimates (at least one from a person wholly unconnected with the landlord) with a further 30-day period. If the contract goes to someone who is neither a nominee nor the lowest estimate, written reasons follow within 21 days of entering into the contract; that is not a third observation period.

The landlord does not have to choose the cheapest estimate, and a tender list of three is a commercial choice rather than a statutory minimum. Two observation periods do not make a 60-day programme: test your own allowances with the Section 20 timeline planner or read how each route works.

### Thresholds and what they do not decide

In England, consultation is required for qualifying works where any one leaseholder’s relevant contribution is more than £250, and for a qualifying long-term agreement where any one leaseholder’s contribution is more than £100 in an accounting period. A qualifying long-term agreement is generally one with a term of more than 12 months, subject to the statutory definition and exclusions; check its notice and renewal terms and the cost for the relevant accounting period.

Use the actual lease shares and the highest relevant contribution, including VAT where payable. Dividing the total equally is only a rough check. Check contributions with the Section 20 checker.

- A one-off professional survey is not physical works simply because its fee exceeds £250 per flat; a longer professional-services appointment may need a separate long-term-agreement check.
- A reserve fund, a majority vote, share of freehold or informal agreement among leaseholders does not by itself remove the consultation requirements.
- Splitting a project into invoices or phases does not create an exemption.
- The thresholds are separate from HCS’s professional fee, and a checker result is not a decision that notices are valid or permission to start work.
Thresholds effective from 31 October 2003; statutory sources checked 16 November 2026. This source check is separate from the page’s human review date. Sources: [qualifying works amount](https://www.legislation.gov.uk/uksi/2003/1987/regulation/6), [agreement amount](https://www.legislation.gov.uk/uksi/2003/1987/regulation/4), [agreement definition and dispensation](https://www.legislation.gov.uk/ukpga/1985/70/section/20ZA).

### Recovery, urgency and other duties

Consultation is a procedural requirement. Following it does not by itself establish that every cost can be recovered. Recovery can also depend on the lease, whether costs are reasonable and the work is of a reasonable standard, lawful demands, the 18-month time limit in [section 20B](https://www.legislation.gov.uk/ukpga/1985/70/section/20B) and [building-safety leaseholder protections](https://www.gov.uk/guidance/building-safety-leaseholder-protections-guidance-for-leaseholders). These are legal questions for the landlord’s advisers and, for a leaseholder, their own.

Urgency does not automatically waive consultation. The First-tier Tribunal may dispense with some or all of the requirements under [section 20ZA](https://www.legislation.gov.uk/ukpga/1985/70/section/20ZA) where it is satisfied that it is reasonable; it considers whether leaseholders were prejudiced and may attach conditions. Applying is not the same as obtaining dispensation. HCS can provide agreed technical evidence, such as the condition record, scope, chronology and cost information, without promising the outcome.

If consultation is not carried out and dispensation is not granted, each leaseholder’s contribution can be limited to £250 for the works, or £100 for each accounting period under a long-term agreement. Whether any shortfall can be funded another way depends on the lease and the circumstances; take legal advice rather than assuming either way.

Planning, listed building consent, building control, CDM duties and specialist fire or structural work are separately scoped; Section 20 consultation does not satisfy them.

### Fees and what the entry fee covers

Initial technical assessment

From £1,800 including VAT

£1,500 professional fee plus £300 VAT at 20%.

The starting fee applies to an initial technical assessment of a single residential building where the written quotation confirms it. It covers:

- Review of the surveys, maintenance records and proposed works you provide.
- Inspection of the agreed accessible elements, or a desktop review where that is agreed instead.
- Identification of evidence gaps, repair options, access issues and any specialist input needed.
- A written technical scope or recommendations for the next stage.
It does not buy the whole consultation, tender and construction programme. Specification and tender, contract administration, larger or multiple buildings, specialist investigations, opening-up, access equipment and further meetings are quoted individually.

The quotation states the site attendance, the documents reviewed, the written output, any meetings and how many revisions are included. None is assumed from the starting fee.

Specification and tender, and contract administration under the chosen building contract, are quoted individually once the building, the scope and the contract are known. Each quotation states its deliverables, inspection allowance, duration assumptions and exclusions.

Timescales are agreed for the actual instruction once documents, access and any deadline have been checked. An enquiry does not reserve an appointment or a response date.

HCS’s professional fee is separate from the construction budget, each leaseholder’s service-charge contribution, the statutory thresholds and any specialist or legal costs. Whether a professional fee can be recovered through the service charge depends on the lease and the applicable rules; an HCS appointment does not guarantee recovery.

### Evidence, independence and responsibility

Professional information: Savas Bulduk BSc (Hons) MRICS, Director & Chartered Building Surveyor. Your written appointment names the responsible professional and their role. Verify the firm’s RICS regulation details.

Related condition appraisals: external condition appraisal and maintenance planning, West Hampstead NW6, condition survey and feasibility, Hampstead Garden Suburb and the redacted block repairs appraisal sample, West Hampstead NW6. These are condition appraisals used in maintenance planning. They are not evidence of a completed consultation, valid notices, cost recovery or completed works, and no Section 20 specification or tender comparison is published as a sample.

Where HCS specifies, tenders or administers a Section 20 programme, HCS will not also tender as contractor. A separate group company name does not by itself resolve a conflict: any connection between HCS’s group and a proposed contractor is disclosed to the client and reviewed under our conflicts policy before tenders are invited, and we tell you when our conflict rules prevent the companies working on the same project. Read how we manage conflicts of interest.

### Related services for blocks in Greenwich

- Contract administration in Greenwich
- Licence to alter surveying in Greenwich
- Party wall advice in Greenwich
- Building condition surveys in Greenwich
- Schedules of condition in Greenwich
- Planned maintenance surveys
Each related service has its own scope and fee; none is included in a Section 20 appointment unless agreed in writing.

### Related pages, tools and guides

- London Section 20 and major works consultancy
- All Section 20 locations
- Surveying services in Greenwich
#### Nearby Section 20 pages

- Section 20 major works in Deptford
- Section 20 major works in Blackheath
- Section 20 major works in Woolwich
#### Tools and guides

- Section 20 contribution checker: compare the highest lease share with the thresholds.
- Section 20 timeline planner: work back through the ordinary route with your own allowances.
- Received a Section 20 notice? A leaseholder checklist: For leaseholders: organise the notice, lease, estimates and technical questions before responding.
- Council major works bills: what an independent surveyor can review: For council leaseholders: separate technical questions from lease and payment advice.
- A major works decision guide for RMC and RTM directors: For boards: client authority, evidence, consultation responsibilities, funding and procurement.
- Understanding Section 20 consultation for major works: How the consultation stages sit alongside the technical programme.
### Ready to discuss the building?

Call 020 7101 4590 or send the enquiry above.

---

Hampstead Chartered Surveyors & Building Consultancy — RICS Regulated Firm No. 923064
020 7101 4590 · enquiries@hampsteadcharteredsurveyors.co.uk
Unit 3, Palace Court, 250 Finchley Road, London NW3 6DN

Source: https://www.hampsteadcharteredsurveyors.co.uk/areas/greenwich-section-20-major-works