Free Party Wall Notice Templates

The official example letters for all three party wall notices, ready to complete and serve.

RICS RegulatedLondonChartered Surveyors
Free Templates

The three party wall notices, ready to serve

Before notifiable works start, the Party Wall etc. Act 1996 requires written notice to every adjoining owner — 2 months ahead for party structure works, 1 month for a new boundary wall or the 3/6-metre excavation cases. The letters below are the Government’s official example letters; complete the [placeholders], keep a copy, and serve one notice per adjoining owner. Not sure which applies? Run the free party wall notice checker first.

1. Party Structure Notice (section 2 works)

Use it when: cutting into, raising, underpinning, thickening, repairing or demolishing a shared wall or structure — steels for a loft, chimney breast removal, underpinning. Minimum notice: 2 months.

To [adjoining owner — note 4], of [adjoining owner’s main address — note 5]. [Date — note 7]. Dear [name, or Sir or Madam — note 8],

As the owner/s of [your address — note 3] which is adjacent to your premises at [the neighbouring address — note 6] I/we [your full name/s — note 1] of [your correspondence address — note 2] notify you that in accordance with our rights under section 2 of the Party Wall etc Act 1996 I/we intend to carry out building works.

The proposed works are: [full description of the works — note 17]. The proposed works do / do not involve special foundations[if they do, attach plans, sections and construction details — note 17].

I/we intend to start works on [date after the 2-month notice period — note 10] [or on the earlier date of [date] with your written agreement].

If you are content for the works to go ahead as proposed please complete, sign and return the attached letter [based on example letters 2 or 3 — note 12] within 14 days of receiving this letter. If you do not confirm in writing that you are content for the work to go ahead as proposed we will be “in dispute” under the Act.

In the event of any dispute between us under the Act, would you be willing to agree to the appointment of an “Agreed Surveyor”? If the answer is yes I suggest using [surveyor’s name and contact details — note 13] but would be happy to receive your alternative proposal. If the answer is no, please let me know whom you would appoint as your surveyor.

Yours sincerely — [building owner’s signature/s (all joint owners) — note 15]

Official version: Example letter 1 — Party Structure Notice (ODT).

2. Line of Junction Notice — new wall astride the boundary (section 1)

Use it when: you want to build a new party wall sitting on the boundary line itself, which needs your neighbour’s written consent. Minimum notice: 1 month.

To [adjoining owner — note 4], of [adjoining owner’s main address — note 5]. [Date — note 7]. Dear [name, or Sir or Madam — note 8],

As the owner/s of [your address — note 3] which is adjacent to your premises at [the neighbouring address — note 6] I/we [your full name/s — note 1] of [your correspondence address — note 2] notify you that in accordance with our rights under section 1 of the Party Wall etc Act 1996 I/we intend to build at the Line of Junction between our properties.

I/we would, with your written permission, like to build a new wall as a party wall astride the boundary. If you are content please complete, sign and return the attached letter [based on example letter 5 — note 12] within 14 days. If I/we do not receive your written permission or you dissent, the wall will be built wholly on my/our own land up to the boundary line.

The proposed works are: [description of the wall — height, length, materials — note 16]. I/we intend to start works on [date after the 1-month notice period — note 10] [or on the earlier date of [date] with your written agreement].

[Only if applicable:] Under the right given by section 1(6) of the Party Wall etc Act it is intended to put projecting foundations under your land. [Only if applicable:] Under section 7(4), with your written permission, I wish to lay special foundations extending under your land.

In the event of any dispute between us under the Act, would you be willing to agree to the appointment of an “Agreed Surveyor”? If the answer is yes I suggest using [surveyor’s name and contact details — note 13] but would be happy to receive your alternative proposal. If the answer is no, please let me know whom you would appoint as your surveyor.

Yours sincerely — [building owner’s signature/s (all joint owners) — note 15]

Official version: Example letter 4 — Line of Junction Notice — new wall astride the boundary (ODT).

3. Line of Junction Notice — new wall wholly on your own land (section 1)

Use it when: you are building a new wall up to (but not on) the boundary — consent is not required, but notice is. Minimum notice: 1 month.

To [adjoining owner — note 4], of [adjoining owner’s main address — note 5]. [Date — note 7]. Dear [name, or Sir or Madam — note 8],

As the owner/s of [your address — note 3] which is adjacent to your premises at [the neighbouring address — note 6] I/we [your full name/s — note 1] of [your correspondence address — note 2] notify you that in accordance with our rights under section 1 of the Party Wall etc Act 1996 I/we intend to build at the Line of Junction between our properties.

The new wall will be built wholly on my/our own land up to the boundary line. The proposed works are: [description of the wall — note 16].

[Only if applicable:] Under the right given by section 1(6) of the Party Wall etc Act it is intended to put projecting foundations under your land. [Only if applicable:] Under section 7(4), with your written permission, I wish to lay special foundations extending under your land.

I/we intend to start works on [date after the 1-month notice period — note 10] [or on the earlier date of [date] with your written agreement].

In the event of any dispute between us under the Act, would you be willing to agree to the appointment of an “Agreed Surveyor”? If the answer is yes I suggest using [surveyor’s name and contact details — note 13] but would be happy to receive your alternative proposal. If the answer is no, please let me know whom you would appoint as your surveyor.

Yours sincerely — [building owner’s signature/s (all joint owners) — note 15]

Official version: Example letter 6 — Line of Junction Notice — new wall wholly on your own land (ODT).

4. Three/Six-Metre Notice — excavation (section 6)

Use it when: foundations, drainage or a basement within 3 metres of a neighbouring structure and deeper than its foundations, or within 6 metres under the 45-degree rule. Minimum notice: 1 month.

To [adjoining owner — note 4], of [adjoining owner’s main address — note 5]. [Date — note 7]. Dear [name, or Sir or Madam — note 8],

As the owner/s of [your address — note 3] which is adjacent to your premises at [the neighbouring address — note 6] I/we [your full name/s — note 1] of [your correspondence address — note 2] notify you that in accordance with our rights under either section 6(1) of the Party Wall etc. Act 1996 that I/we intend to build within 3 metres of your building and to a lower level than the bottom of your foundations, or section 6(2) that I/we intend to build within 6 metres of your building and to a level below a line drawn at 45° downwards towards my adjacent land from the bottom of your foundations, by carrying out the works detailed below.

The proposed works are: [description of the excavation and works — note 18]. The accompanying plans and sections show the site of the proposed building and the excavation depth proposed — the Act requires these drawings.

I/we do / do not propose to underpin or otherwise strengthen in order to safeguard the foundations of your property.

I/we intend to start works on [date after the 1-month notice period — note 10] [or on the earlier date of [date] with your written agreement].

If you are content for the works to go ahead as proposed please complete, sign and return the attached letter [based on example letters 9 or 10 — note 12] within 14 days of receiving this letter. If you do not confirm in writing we will be “in dispute” under the Act.

In the event of any dispute between us under the Act, would you be willing to agree to the appointment of an “Agreed Surveyor”? If the answer is yes I suggest using [surveyor’s name and contact details — note 13] but would be happy to receive your alternative proposal. If the answer is no, please let me know whom you would appoint as your surveyor.

Yours sincerely — [building owner’s signature/s (all joint owners) — note 15]

Official version: Example letter 8 — 3/6 Metre Notice (excavation) (ODT).

Letters adapted from the example letters in the Party Wall etc. Act 1996 explanatory booklet © Crown copyright, reused under the Open Government Licence v3.0. Not legal advice; we confirm the correct notices for your project before anything is served.

Completion Notes

How to complete the placeholders

  • Note 1 — Building Owner: the owner of the premises where the work is proposed. Joint owners must all be named.
  • Note 2 — Building Owner’s main address: your correspondence address, which may differ from the works address.
  • Note 3 — Building Owner’s building: the address of the premises where the work is proposed.
  • Note 4 — Adjoining Owner: the neighbour’s full name/s if possible; write “The Owner” if unknown.
  • Note 5 — Adjoining Owner’s main address: the owner’s main address if a landlord; otherwise the adjacent premises.
  • Note 6 — Adjoining Owner’s building: the address of the premises adjacent to the works.
  • Note 7 — Date: the date the notice is posted or served — always date the letter.
  • Note 8 — Title: full name/s if known, otherwise “Sir or Madam”.
  • Note 9 — Explanatory booklet: give your neighbour the GOV.UK booklet link so they understand why you are serving notice.
  • Note 10 — Date of works: must be after the notice period ends: 2 months for a Party Structure Notice, 1 month for Line of Junction and 3/6-Metre Notices.
  • Note 11 — Early start: you may start earlier only with your neighbour’s written agreement.
  • Note 12 — Attached letter: prepare a reply letter for your neighbour based on the acknowledgement templates (2/3, 5/7 or 9/10).
  • Note 13 — Agreed Surveyor’s name: give the name, address and telephone number of your proposed agreed surveyor; the neighbour may propose an alternative.
  • Note 14 — Email address: notices can be emailed only if the recipient confirms willingness and provides an address.
  • Note 15 — Signature: all joint owners should sign, and print names, unless one is authorised to sign for all.
  • Note 16 — Description of the wall: height, length and materials of the new wall at the line of junction.
  • Note 17 — Description of the works: full details of works affecting the party structure; special foundations need plans, sections and construction details.
  • Note 18 — Excavation description and drawings: a simple description suffices if drawings clearly show the depth and location; the Act requires those drawings, and you must state whether you propose to safeguard the neighbouring foundations.
Served Correctly

Rather have the notices handled?

A defective notice can invalidate the whole process. Send your drawings and the neighbouring addresses and we will confirm, prepare and serve the right notices.

Prefer to talk it through first? Call 020 7101 4590.

FAQs

Common questions about serving notices

Are these templates free to use?

Yes. They are the Government’s official example letters from the Party Wall etc. Act 1996 explanatory booklet, reproduced under the Open Government Licence v3.0. You can serve notices yourself using them.

Which notice do I need?

Work to a shared structure needs a Party Structure Notice (2 months); a new wall at the boundary needs a Line of Junction Notice (1 month); excavation within the 3 or 6-metre zones needs a section 6 notice (1 month). Our free notice checker walks through the questions.

What if my neighbour ignores the notice?

If there is no written consent within 14 days a dispute is deemed to have arisen and surveyors are appointed under section 10 of the Act to agree a party wall award.

Can a defective notice cause problems?

Yes. A notice missing required details, drawings or the correct notice period can be invalid, and works started on an invalid notice risk an injunction. Many owners have a surveyor prepare and serve the notices for that reason.