Set the vertical limits of a Golders Green parade claim
Barnet's Golders Green appraisal records purpose-built parades with shops at street level and homes above. A commercial dilapidations schedule should therefore identify the floor and component actually covered by the lease instead of treating the whole elevation as one business demise. Mark shopfronts, upper windows, roofs, entrances and service routes against the executed plan and the current arrangement. Confirm separately controlled accommodation and shared building provisions. The appraisal describes local building form; it neither transfers residential fabric to a shop tenant's obligations nor establishes who presently occupies each part or which route is available for an inspection.
Obtain the lease, supplemental agreements, alteration licences and any incorporated condition evidence before classifying alleged breaches. A damaged finish, altered shopfront and retained roof may involve different covenants, inspection evidence and remedies. State what was observed directly and what depends on information supplied by others. If an inaccessible upper element is included in an allegation, identify the access or specialist examination needed rather than implying it was inspected from within the shop. The cost schedule should make its quantities and scope intelligible, allowing the response to distinguish a contractual disagreement from a concern about the proposed repair technique.
Local evidence: Barnet: Golders Green Town Centre appraisal, August 2011, section 2.2.
Describe Accommodation Road and St Albans Lane access item by item
The appraisal identifies Accommodation Road and St Albans Lane behind the shopping parades, with adapted service buildings and business uses in its account. Inspect the chosen route's current entrances, clearance and control before relying on it for a repair operation. Historic service use does not grant a tenant or landlord unrestricted unloading, scaffold or storage rights today. Record how equipment and materials would pass to the workface and which other accesses must remain available. Any allowance for handling or temporary protection should identify the actual constraint rather than treating every Golders Green rear lane as an equivalent working environment.
The RICS professional standard informs preparation of dilapidations schedules and related advice. Agree whether the instruction concerns the term, termination or checking completed work, and preserve a dated photographic record with stable item numbers. Separate repairs from decoration and from reinstatement under the relevant lease or alteration licence. If the chosen route later proves unavailable, trace the revised method and estimate to the affected item. A change in practical access should not quietly expand the alleged breach or justify unrelated improvements. Where concealed fabric or installations require testing, define the additional instruction and make any provisional assumptions explicit in the advice.
Local evidence: Barnet: Golders Green Town Centre appraisal, August 2011, section 2.2; RICS: Dilapidations in England and Wales.
Do not infer Golders Green redevelopment from transport proximity
Barnet locates the rail, bus and coach interchange at the junction of Finchley Road with Golders Green Road and North End Road. That transport setting may help locate the premises and explain access questions; it does not establish a landlord's redevelopment plan or a particular valuation outcome. Request the actual post-tenancy scheme, evidence of decisions and intended timing. Identify the shops, upper parts or retained structures it would affect. A general intention to refresh a unit should be distinguished from an evidenced proposal that would remove a component or render a particular scheduled repair unnecessary after possession is returned.
Where repairing-covenant damages are pursued, consider the section 18(1) diminution limit and specified demolition or structural-alteration circumstances with legal and valuation advisers. Apply that analysis to the relevant obligation rather than reducing the entire schedule by a generic percentage. For supersession, demonstrate the relationship between each disputed remedy and the landlord's actual proposed work. The Quantified Demand needs a substantiated account of likely loss, which is not necessarily the total of a repair estimate. Neither transport accessibility nor a neighbouring scheme establishes the present premises' demand, future use or the recoverability of every quoted item.
Local evidence: Barnet: Golders Green Town Centre appraisal, August 2011, section 2.2; Landlord and Tenant Act 1927, section 18.
Keep railway-arch and highway evidence separate from the lease obligation
The local character account identifies railway arches off Finchley Road as a distinct part of Golders Green's setting. If the instructed premises involve an arch or works near railway land, establish the actual property limits and required technical input before specifying fixings, penetrations or access. A parade detail is not automatically suitable for that structure. Barnet's licence information also distinguishes temporary street operations; check what the actual method needs. Infrastructure agreement, highway permission and the tenant's contractual responsibility answer different questions. Record each clearly so that a proposed operation is not treated as authorised merely because one document has been obtained.
Use the Dilapidations Protocol for commercial termination disputes within its scope to present the schedule, Quantified Demand and response with clear supporting evidence. Explain alleged breaches, remedies, costs and likely loss, including relevant landlord intentions. Keep inspections and subsequent works dated so that changing conditions can be distinguished from the original allegation. If a railway interface or access permission remains unresolved, disclose its effect on the method and estimate. This enables proportionate discussion of the actual disputed items without assuming that an infrastructure-related cost is either automatically the tenant's liability or irrelevant to the landlord's claim.
Local evidence: Barnet: Golders Green Town Centre appraisal, August 2011, section 2.2; Barnet: highways construction licence types; Civil Procedure Rules: Dilapidations Protocol.
Golders Green lease-end questions
Does a Golders Green shop tenant repair all floors above the frontage?
The executed lease and relevant building provisions determine the obligation. The appraisal records shops with homes above but cannot allocate repair responsibility. Identify the actual demise, roof and window covenants, shared components and inspection access before including upper-building items in the schedule.
Are Accommodation Road and St Albans Lane automatically usable for works?
No. Confirm present control, clearance, occupation and access rights for the chosen operation. The appraisal's description of service uses does not grant unloading or scaffold permission. State any unresolved assumption and explain its effect on the estimated remedy rather than applying a general rear-access allowance.
Does the interchange support an automatic redevelopment defence?
No. Obtain the landlord's evidenced intentions for the actual premises and connect them to particular scheduled repairs. Transport proximity alone establishes neither supersession nor the statutory section 18 outcome. Appropriate legal and valuation advice should address repairing-covenant damages and the separate bases of other claimed obligations.
Should a railway arch claim use the neighbouring parade specification?
Only where the actual construction and competent advice support that method. Establish structure, property limits, permissions and the relevant lease obligations first. Record infrastructure requirements separately from highway approvals, and explain how any unresolved technical or access issue affects the proposed repair and its cost.
Related guidance: London dilapidations advice; lease condition records; licence to alter.
Golders Green Schedule of Dilapidations Enquiry (From £1,250 plus VAT)
Content updated: October 2026.
Other Golders Green surveying services
Need a RICS survey quote in Golders Green? We confirm a fixed fee after scoping. Call 020 7101 4590, email enquiries@hampsteadcharteredsurveyors.co.uk, or inspect our redacted RICS Level 3 sample reports. Sample reports.