Who appoints HCS
HCS acts for the client named in the written appointment. For major works this is usually the landlord or freeholder, a resident management company (RMC), a right to manage (RTM) company or the managing agent acting with their authority. Leaseholders who pay for the works through the service charge are not automatically HCS’s clients, and HCS does not represent them unless they appoint HCS separately.
Before accepting an instruction we check the building, the parties and any existing appointment. HCS will not act against an existing landlord or managing-agent client on the same matter, and does not act for both sides of a disagreement about the same works.
For boards, freeholders and managing agents planning works
Commission the work in stages and start from the point you have reached. Each stage has its own written scope and fee, agreed before instruction, so you do not have to buy the whole programme at the outset.
- Condition evidence and scope. Review the surveys, maintenance records and proposed works you hold, inspect the agreed elements and set out a technical scope or recommendations for the next stage.
- Specification and tender. Prepare a specification or schedule of works that every contractor prices on the same basis, run the tender and compare the returns technically and commercially.
- Contract administration. If separately appointed, administer the building contract you choose: inspections at agreed intervals, instructions, valuations, completion and the defects period.
Already have a specification, tenders or a contractor? We can review what exists, for example whether the tenders priced the same scope and what each excludes or leaves provisional, without repeating earlier stages. Tell us which documents have already been issued to leaseholders.
If you have received a Section 20 notice
A leaseholder, a group of leaseholders or a residents’ association can ask for a separately scoped technical review. Depending on the documents available, it can look at:
- the proposed scope and the reasons given for it;
- the surveys or condition evidence the proposal relies on;
- whether the specification describes the work clearly enough to price;
- whether the estimates were priced on a comparable basis, including exclusions, provisional sums and access assumptions; and
- technical questions to put to the landlord or managing agent during the consultation.
Questions about the lease, whether a notice is valid, tribunal strategy and whether you have to pay may need a solicitor or other legal adviser. A technical review does not by itself stop the works, cancel a demand or reduce a bill.
Tell us who the landlord and managing agent are and any response deadline stated in the notice before you send documents. We check for conflicts first: if HCS already acts for the landlord or agent on the same building, we cannot act for you on that matter. We confirm whether we can help, and by when, only after checking the deadline; an enquiry does not reserve an appointment.
Major works context in Lewisham
These documentary sources describe parts of Lewisham at their publication dates. Use them to frame questions about the actual building; they do not establish its condition, the leases, the consultation route or who must pay.
Around a single park the built form changes sharply. Adopted in June 2019, the Lewisham Park Conservation Area Appraisal and Management Plan identifies three key forms: Victorian semi-detached houses, Edwardian semi-detached and detached houses, and three tower blocks dating to 1965. It also records that the Edwardian houses largely remain in single family use, while the Victorian houses have been subdivided into flats.
Eight pairs of three-storey villas stand on the southern side of the park, in yellow stock brick with gabled bays rising to full height. At first floor, French windows open onto terraces on top of the ground-floor projecting bays.
What this means for a major works brief
Blocks, mansion flats and shared parts
Where a building matches the blocks or mansion flats described in these sources, list the shared roofs, elevations, staircases, lifts and services that the proposed works cover. The leases, not the building type, decide who contributes and in what share, so supply the leases or a lease summary with the enquiry.
Converted houses and lease boundaries
For a house converted into flats, identify which roof, walls, windows, foundations and drains the landlord retains and which belong to individual flats. Conversions combine original fabric with later alterations, so the specification should separate common items from work inside a flat.
Conservation context and consents
Check any conservation-area designation or listing at the actual address before the specification is fixed. Planning and listed building consent are separate from Section 20 consultation and can change the repair detail, the tender scope and the programme.
Local sources and research limits
- Lewisham: Lewisham Park Conservation Area Appraisal and Management Plan, adopted 26 June 2019
- Lewisham: St Mary's Conservation Area Character Appraisal, adopted 12 December 2006
- Lewisham: adopted Local Plan 2020 to 2040, Policy QD9
- Lewisham: Article 4 directions
The descriptions are retained from maintained, attributed local research reused on 16 November 2026. They are documentary context, not a current inspection of any building.
What each stage produces
Initial assessment: a review of the surveys, records and proposed works, inspection of the agreed accessible elements (or an agreed desktop review), the evidence gaps, repair options, access issues and specialist input, and a written technical scope or recommendations for the next stage.
Specification and tender: one consistent scope for every contractor to price, a record of tender queries, exclusions, provisional items and access assumptions, a reasoned comparison with a recommendation, and technical information for the landlord’s consultation documents.
Delivery support, if separately appointed: the contract-administration duties under the chosen contract, with an agreed inspection frequency, instructions, variation records, payment assessments, completion and the defects period. It is not continuous supervision and does not certify concealed work or prevent every variation.
Missing documents, newly found defects or changed proposals can change the scope; any change to the scope and fee is agreed in writing first. See each stage’s outputs in full.
How consultation fits the technical work
The landlord or managing agent must identify the consultation route. Ordinary qualifying works without a public-notice requirement follow Schedule 4, Part 2; works needing public notice, proposed long-term agreements and works under an existing agreement follow different schedules, and an uncertain route needs advice before the first notice.
On the ordinary route, the landlord or agent issues a notice of intention with a 30-day period for observations and nominations, obtains estimates, then issues a statement of at least two estimates (at least one from a person wholly unconnected with the landlord) with a further 30-day period. If the contract goes to someone who is neither a nominee nor the lowest estimate, written reasons follow within 21 days of entering into the contract; that is not a third observation period.
The landlord does not have to choose the cheapest estimate, and a tender list of three is a commercial choice rather than a statutory minimum. Two observation periods do not make a 60-day programme: test your own allowances with the Section 20 timeline planner or read how each route works.
Thresholds and what they do not decide
In England, consultation is required for qualifying works where any one leaseholder’s relevant contribution is more than £250, and for a qualifying long-term agreement where any one leaseholder’s contribution is more than £100 in an accounting period. A qualifying long-term agreement is generally one with a term of more than 12 months, subject to the statutory definition and exclusions; check its notice and renewal terms and the cost for the relevant accounting period.
Use the actual lease shares and the highest relevant contribution, including VAT where payable. Dividing the total equally is only a rough check. Check contributions with the Section 20 checker.
- A one-off professional survey is not physical works simply because its fee exceeds £250 per flat; a longer professional-services appointment may need a separate long-term-agreement check.
- A reserve fund, a majority vote, share of freehold or informal agreement among leaseholders does not by itself remove the consultation requirements.
- Splitting a project into invoices or phases does not create an exemption.
- The thresholds are separate from HCS’s professional fee, and a checker result is not a decision that notices are valid or permission to start work.
Thresholds effective from 31 October 2003; statutory sources checked 16 November 2026. This source check is separate from the page’s human review date. Sources: qualifying works amount, agreement amount, agreement definition and dispensation.
Recovery, urgency and other duties
Consultation is a procedural requirement. Following it does not by itself establish that every cost can be recovered. Recovery can also depend on the lease, whether costs are reasonable and the work is of a reasonable standard, lawful demands, the 18-month time limit in section 20B and building-safety leaseholder protections. These are legal questions for the landlord’s advisers and, for a leaseholder, their own.
Urgency does not automatically waive consultation. The First-tier Tribunal may dispense with some or all of the requirements under section 20ZA where it is satisfied that it is reasonable; it considers whether leaseholders were prejudiced and may attach conditions. Applying is not the same as obtaining dispensation. HCS can provide agreed technical evidence, such as the condition record, scope, chronology and cost information, without promising the outcome.
If consultation is not carried out and dispensation is not granted, each leaseholder’s contribution can be limited to £250 for the works, or £100 for each accounting period under a long-term agreement. Whether any shortfall can be funded another way depends on the lease and the circumstances; take legal advice rather than assuming either way.
Planning, listed building consent, building control, CDM duties and specialist fire or structural work are separately scoped; Section 20 consultation does not satisfy them.
Fees and what the entry fee covers
Initial technical assessment
From £1,800 including VAT
£1,500 professional fee plus £300 VAT at 20%.
The starting fee applies to an initial technical assessment of a single residential building where the written quotation confirms it. It covers:
- Review of the surveys, maintenance records and proposed works you provide.
- Inspection of the agreed accessible elements, or a desktop review where that is agreed instead.
- Identification of evidence gaps, repair options, access issues and any specialist input needed.
- A written technical scope or recommendations for the next stage.
It does not buy the whole consultation, tender and construction programme. Specification and tender, contract administration, larger or multiple buildings, specialist investigations, opening-up, access equipment and further meetings are quoted individually.
The quotation states the site attendance, the documents reviewed, the written output, any meetings and how many revisions are included. None is assumed from the starting fee.
Specification and tender, and contract administration under the chosen building contract, are quoted individually once the building, the scope and the contract are known. Each quotation states its deliverables, inspection allowance, duration assumptions and exclusions.
Timescales are agreed for the actual instruction once documents, access and any deadline have been checked. An enquiry does not reserve an appointment or a response date.
HCS’s professional fee is separate from the construction budget, each leaseholder’s service-charge contribution, the statutory thresholds and any specialist or legal costs. Whether a professional fee can be recovered through the service charge depends on the lease and the applicable rules; an HCS appointment does not guarantee recovery.
Evidence, independence and responsibility
Professional information: Savas Bulduk BSc (Hons) MRICS, Director & Chartered Building Surveyor. Your written appointment names the responsible professional and their role. Verify the firm’s RICS regulation details.
Related condition appraisals: external condition appraisal and maintenance planning, West Hampstead NW6, condition survey and feasibility, Hampstead Garden Suburb and the redacted block repairs appraisal sample, West Hampstead NW6. These are condition appraisals used in maintenance planning. They are not evidence of a completed consultation, valid notices, cost recovery or completed works, and no Section 20 specification or tender comparison is published as a sample.
Where HCS specifies, tenders or administers a Section 20 programme, HCS will not also tender as contractor. A separate group company name does not by itself resolve a conflict: any connection between HCS’s group and a proposed contractor is disclosed to the client and reviewed under our conflicts policy before tenders are invited, and we tell you when our conflict rules prevent the companies working on the same project. Read how we manage conflicts of interest.
Section 20 and major works questions
What should a major works brief in Lewisham clarify first?
Where a building matches the blocks or mansion flats described in these sources, list the shared roofs, elevations, staircases, lifts and services that the proposed works cover. The leases, not the building type, decide who contributes and in what share, so supply the leases or a lease summary with the enquiry.
How should a Lewisham brief deal with converted houses and lease boundaries?
For a house converted into flats, identify which roof, walls, windows, foundations and drains the landlord retains and which belong to individual flats. Conversions combine original fabric with later alterations, so the specification should separate common items from work inside a flat.
Does HCS prepare or serve Section 20 notices?
HCS does not prepare or serve statutory Section 20 notices. HCS provides the specification, tender information and consultation support the landlord or managing agent needs. The notices are issued by the landlord or agent, with their solicitor where required. HCS does not give legal advice.
Who appoints HCS, and can leaseholders use the service?
HCS acts for the client named in the written appointment, usually the landlord, freeholder, RMC or RTM company, or a managing agent acting with their authority. Leaseholders who pay through the service charge are not automatically our clients. A leaseholder or residents’ association can ask for a separately scoped technical review once we have checked for conflicts; we will not act against an existing landlord or managing-agent client on the same matter.
How long does Section 20 consultation take?
The ordinary qualifying-works route includes two 30-day observation periods. Preparing the specification, tendering, considering observations and mobilising add further time, so the two periods do not make a 60-day programme. Other routes differ, and the landlord or agent and their adviser confirm the actual dates.
Does the landlord have to choose the cheapest estimate?
No. The landlord must have regard to observations. Under the ordinary route, if the contract goes to someone who is neither a nominated contractor nor the lowest estimate, it must give written reasons within 21 days of entering into the contract. A tender recommendation should explain differences in scope, qualifications, programme and price.
What does the starting fee include?
The initial technical assessment starts from £1,800 including VAT (£1,500 plus £300 VAT at 20%). The starting fee applies to an initial technical assessment of a single residential building where the written quotation confirms it. It covers the document review, the agreed inspection or desktop review and a written technical scope or recommendations. Specification and tender, and contract administration under the chosen building contract, are quoted individually once the building, the scope and the contract are known. Each quotation states its deliverables, inspection allowance, duration assumptions and exclusions.
Can HCS also tender as the contractor?
Where HCS specifies, tenders or administers a Section 20 programme, HCS will not also tender as contractor. A separate group company name does not by itself resolve a conflict; any group connection with a proposed contractor is disclosed and reviewed first.
Send a Section 20 enquiry
Start with your role, the building and what you need. Further details are optional, and “not sure” is a valid answer.
Related services for blocks in Lewisham
- Contract administration in Lewisham
- Licence to alter surveying in Lewisham
- Party wall advice in Lewisham
- Building condition surveys in Lewisham
- Schedules of condition in Lewisham
- Planned maintenance surveys
Each related service has its own scope and fee; none is included in a Section 20 appointment unless agreed in writing.