Identify the block or the house on its own street
The London Borough of Hounslow designated the Stamford Brook Conservation Area on 13 January 1998 and adopted its appraisal in January 2021. The appraisal notes that the busy road along the north side of the common, and the houses beyond it, are outside the borough, and that the Ravenscourt and Starch Green Conservation Area to the east is in Hammersmith and Fulham, so check which council covers the address.
According to the appraisal, development around the common came in three phases: the two listed houses; four storey Victorian flats at the end of Stamford Brook Avenue and three and four storey mansion blocks built between 1901 and 1905; and two storey semi-detached and short terraced houses built between 1907 and 1933. It says the blocks all have balconies of some form and original sash windows.
In a mansion block, a leaseholder proposing a new opening should mark the apartment, floor and staircase as well as the postal address. Include a vertical section if the proposed support meets a separating floor or a wall extending into another unit. Where cutting into a party structure is within section 2 of the Party Wall etc. Act 1996, section 3 deals with the party structure notice. A conversation on a shared landing cannot establish what lies behind the plaster or which owner should receive a notice.
A repair confined to the finish of an existing balcony needs its own description. If it would involve removing a support or cutting into masonry serving two units, put that junction on the drawing. Keep records of repairs that have changed the balcony since construction of the block. A photograph of the front can help identify the bay without settling how the slab or bracket is supported inside.
Across a pair on Prebend Gardens
In Pleydell Avenue the appraisal finds larger houses on the western side with prominent and decorative gables and decorative roof tiles. Prebend Gardens has two storey terraces of four houses on the western side and mostly two storey semis on the eastern, while houses on the common's south side west of Pleydell Avenue have half-timbered gables, brick with a rendered first floor and decorated timber porches.
For a rear extension, draw the garden elevation as it is today. Show the difference between an original wall, a later infill and a proposed wall at the line of junction. Section 1 may be relevant to the last of these. A contractor's plan showing only the internal layout of the enlarged kitchen can leave both owners unable to tell whether the outside face of the wall is set at, beyond or back from the boundary.
An excavation for a footing or a drainage chamber is another operation. For section 6 establish the distance to the nearest neighbouring structure and the relevant foundation depths, including the return of any existing rear extension. Use a common datum when recording levels. If the depth of the older foundation is unknown, show it as unknown and agree what evidence the engineer needs before the building owner tries to fix a start date.
A usable schedule for a gable, roof or stair
Before the builder opens the gable edge, agree the scope of a schedule of condition. Record the adjoining upper room, ceiling junction and external face visible from permitted positions. Identify decorative tiles or an existing repair by location. If a matching detail appears on a second gable, include an overall image so that the two cannot be confused later. An intact painted surface is evidence of its appearance when seen, not a survey of the timbers behind it.
Where a common staircase provides access to two flats, identify the person authorised to arrange the visit and the residents who will be entering and leaving. Agree which part needs to be clear for photographs and whether a second appointment is needed for the roof. A subsequent request for scaffold access has a different purpose and should describe the position, period and arrangements to protect the entrance.
Council and private approvals at the borough boundary
The appraisal’s reference to the borough boundary is a reminder to use the correct council records for the exact plot. Do not assume that a nearby property’s permission or designation establishes the position at your address.
Keep the relevant planning decision, building control material and any landlord's licence with the plans. Cross-reference their issue numbers. A revision made to satisfy a council requirement may move a proposed cheek or beam closer to the adjoining structure. Give that revision to the party wall surveyor so the notice or award can be checked against the construction detail. Permission concerning the appearance of the gable does not determine rights of entry to the adjoining house.
For the owner of the flat or semi next door
If you receive a notice, note its date of receipt and keep the drawings attached. Mark the position of your rooms or the return of your extension if it is unclear on the designer’s plan. Our advice for adjoining owners explains the response choices. A resident may be able to arrange access to a sitting room but need the managing agent to open the adjacent common stair.
Stamford Brook party wall questions
An apartment is on the opposite side of a staircase. Can its plan help?
It can help orient the inspector, but the proposed bearing and adjoining structure need to be located in the actual flats. The floor plan for another entrance cannot show where work would cut into this wall.
If the common is in Hounslow, which council should I look up?
Find the authority for the exact address and use the applicable designation map. The adopted appraisal identifies the edge of the borough at the common. Keep the property-specific decision with the works drawings.
What if we change a proposed footing after the neighbour has replied?
Supply the revised section and the reason for the change. Ask the surveyor to assess the location and depth of the new excavation and whether the earlier documents still cover what is to be built.