Which pair and which roof?
Greenwich’s appraisal identifies three-storey paired gabled villas at 123–125 and 130–136 Coleraine Road, with verandahs and ornamental ironwork. It also records gabled dormers, decorative bargeboards and stucco bays in that group.
The appraisal distinguishes the two-storey group at 60–78 Coleraine Road, with paired doorways and terracotta dates of 1897 or 1898, from the taller villas nearby. A datestone is a useful historical marker, but it cannot date every extension, roof change or internal alteration in the building behind it.
For an alteration on Coleraine Road, put the street number and elevation on the detail for the proposed work. Where a beam for a loft room would be let into dividing masonry, show the pocket, remaining wall and roof framing on both sides. A builder pricing the new beam may not have allowed for the neighbouring roof junction or the temporary weather protection it will need. Those details matter to the owner on the other side before work begins.
Section 2 of the Party Wall etc. Act 1996 concerns specific rights to carry out work to party structures. Where the right applies, the party structure notice is given under section 3. Identify any chimney or raised wall affected by the intended cutting or raising. Where the intended work instead leaves the dividing masonry untouched, establish how the proposed structure is supported before assuming the same notice route applies.
Compare the levels at the rear of the house
The appraisal identifies Westcombe Park Road as the higher part of the study area and describes streets responding to the slope.
For a basement, extension or new pad foundation, put the neighbour's building and its nearest return on the site survey. Then show the proposed excavation and any reliable information about the neighbouring foundation on a section through the closest point. Section 6 uses the distance to a building or structure and depth tests. Taken alone, a photograph looking downhill from the front step cannot determine them.
A line of junction notice under section 1 concerns the proposed wall at the boundary. A wall wholly set back, one on the line and an excavation close to a neighbouring building present different questions. Distinguish the outer wall face, the edge of the footing and the extent of temporary excavation on the same drawing. Identify who has agreed the location of the boundary and flag a discrepancy before basing an instruction on it.
What a pre-works inspection can record
The appraisal says the late-Victorian groups are normally two or two-and-a-half storeys, with varied plans, often highly ornamented facades and pitched or hipped roofs on which pointed gables are characteristic. The Edwardian groups, it says, are pairs or terraces, two storeys high, with pitched roofs, projecting double-height bays and decorative timberwork. It names yellow stock and red brick, natural slate or red-brown clay tiles, and timber, terracotta and stucco detailing as the traditional palette.
A condition record beside a proposed roof opening should allow a second visitor to identify the precise bay, cornice, gable or ceiling inspected. Take a wider view before close images showing existing marks. Include the underside of a verandah where it can be reached safely, and indicate the viewpoint used for high-level ornament. The photograph that establishes how a piece of ironwork looked on the day does not tell how its concealed fixing was made.
Request records for repairs, replacement supports and alterations to doors or windows opening onto it. Identify the roof and eaves above separately from the entrance detail below. A frontage photograph may show the architectural arrangement without revealing concealed connections or the extent of previous work.
If the subject is an apartment, identify the unit, stair and floor as well as the street name. Greenwich's appraisal also records later blocks on Beaconsfield Road and Coleraine Road. A room described as the front room of the neighbouring premises on a villa plan may have no counterpart in a block of flats. Arrange entry to the right unit and ask the manager about views of common areas relevant to the proposed work.
Drawings, council decisions and access
Greenwich's appraisal provides evidence of building types and street characteristics. Look up the actual planning history and any relevant designation for the precise address. A planning approval for how an altered roof will look is separate from building regulations, the private interests in the structure and an award authorising particular works under the Act. Keep a numbered drawing list and use it to check whether a design amendment has shifted the proposed construction towards the neighbouring building.
Before scaffolding is considered, identify any gate, path or steps a person would need to use for an inspection. Agree the inspection purpose and date. If a later construction access request is made, give its purpose, limits, protection and reinstatement arrangements. On a site where the ground falls, indicate which level of a garden or landing the proposed access would occupy.
For the adjoining owner downhill of the work
If a neighbour's section puts the two gardens at the same level, give the surveyor a measured level or photographs showing the steps and identify the room beyond. Keep the notice with all its drawings and date of receipt. Our guidance for adjoining owners explains the choices available. Tell the surveyor if the lower part can only be reached through a separate flat or side entrance.
Westcombe Park party wall questions
Does a dated panel on a house establish the age of its rear footing?
It helps identify the historic front group. Trace the construction of the rear part, check relevant drawings and ask what can establish the actual footing involved in the proposed excavation.
Can I use an existing photograph of a verandah as the condition schedule?
Supply it with its date and position. Agree a current pre-works record of the relevant parts, including where the surface is hidden or access prevents a closer view.
The proposed loft opening is now one bay further back. What should I send?
Provide the replacement drawing with a revision mark, the former location and the new bearing detail. That lets the surveyor assess whether the previous notice or award describes the work that will be built.