The short answer
A Level 3 survey covers the structure and fabric that can be safely accessed: roofs, walls, windows, floors, damp, timber, visible services, drainage and the immediate site. On the day Savas inspects the property himself, usually for 2 to 3 hours for a typical house or flat, and the report usually follows within about 5 working days.
What Savas checks
- Roofs, chimneys, gutters and downpipes, from the ground, from windows and, where agreed, by drone.
- External walls, pointing, render, windows and doors.
- The loft and roof timbers where there is safe access.
- Each room: ceilings, walls, floors and joinery, with signs of movement or damp, and moisture readings where useful.
- Visible services, accessible drainage, boundaries and the site.
- Alterations and extensions, so you know what to ask your solicitor about consents.
Furniture, stored belongings and fitted floor coverings can limit what is seen, and the report records those limits. Larger or heavily altered buildings take longer on site. If Savas finds anything urgent, he calls you about it first, before the written report.
When to call a specialist
The report highlights urgent or safety-related items separately and says where specialist investigation is needed, such as a drainage CCTV survey, electrical and gas tests, a structural engineer or opening-up. Where you can, arrange these before exchange.
Answered by
Savas Bulduk BSc (Hons) MRICS, Director & Chartered Building Surveyor
Topic
Related service
A typical enquiry
A buyer of a Victorian house in NW6 with a rear extension and a loft conversion asks what happens on the inspection day. In a case like this the most useful step is to send the listing, floor plan and any papers for the extension and loft before the visit, so Savas can look hardest at the parts most likely to raise structural or consent questions.
This example is generalised from the kinds of enquiry we receive. Names, addresses and other identifying details are not used.