New-build snagging surveys in Ripley

Understand the visible condition of the agreed new home or newly completed work, with a numbered photographic snagging schedule. For buyers, owners and other clients whose appointment and report use are agreed in advance.

Request a fixed snagging-survey quote

Choose the inspection stage

Before legal completion

Establish the applicable scheme, notice to complete, property readiness, access and required checklist before agreeing the visit.

Enquire about this stage

After handover

Record visible workmanship, incomplete work and functional concerns in the agreed accessible parts of the home.

Enquire about this stage

Before a reporting deadline

Identify the actual developer arrangement or warranty policy, dates and previous notifications. There is no universal two-year snagging deadline.

Enquire about this stage

Reinspection of reported items

Use the original schedule and agreed items. Record unresolved, apparently rectified, inaccessible and newly identified matters separately.

Enquire about this stage

Not sure which route fits? Select not sure and describe your dates. You do not need to understand the scheme before contacting us.

Planning your Ripley instruction

Use the development name and plot or unit number as well as the street address and postcode. A sales plot number may differ from the postal address. Send the site plan if that is the clearest way to identify the home and entrance.

  • For an apartment, identify the floor, private rooms, balcony and any common areas you want considered. Arrange the relevant permissions; an inspection of the unit does not assess the whole block.
  • For a house, identify the plot boundary and which garage, garden, drainage access points and external elements form part of the proposed appointment.
  • For a newly completed conversion, separate the new work from retained fabric on the plans. Older roofs, walls or concealed alterations may need a separate condition survey or defect investigation.

The actual home, agreed work and access determine the inspection. Please identify any shared areas separately from the private unit.

Ripley area information provides wider property context; it does not establish the condition of your home.

What is checked, and the limits

A snagging survey is a non-invasive inspection of the agreed accessible property, recording observations at the inspection date. The appointment may cover finishes, fitted joinery, doors and windows, kitchens and bathrooms, visible fixtures and accessible external elements.

  • Visual observation: record visible workmanship, damage, incomplete work and concerns, including location and access limits.
  • Ordinary operation: appropriate normal-use checks of fixtures or controls where permitted, safe and within the agreed appointment. A normal-use check is not system commissioning or certification.
  • Measurements: proportionate measurements against relevant, established project criteria where appropriate to the equipment, access and scope.
  • Specialist work: electrical or gas testing, heating commissioning, ventilation balancing and fire-system certification require the relevant specialist scope. They are not implied by a snagging visit.

A visible cylinder, alarm, ventilation terminal or door fitting does not establish the performance or compliance of the whole system. MVHR balancing, fire-door certification, concealed fire-stopping or riser collars, cavity trays, waterproofing and hidden insulation are not verified by looking at exposed finishes. Thermal imaging, moisture readings, drones, opening-up and specialist tests are not automatically included; any separately agreed method has its own purpose and limitations.

For an apartment, agree the private unit and any accessible common areas expressly included. There is no assumed access to plant rooms, risers, lift equipment or inaccessible roofs, and no whole-block external-wall or fire-stopping assessment. Newly completed conversions may retain older fabric requiring a separate defect investigation or appropriate home survey.

Significant visible safety concerns are flagged with the need for appropriate specialist advice. Agree the contact and communication arrangements before inspection; a snagging appointment is not an emergency response service. Concealed or intermittent defects may not be apparent at the visit.

What you receive

The written snagging schedule uses numbered observations with rooms or elements, photographs and clear descriptions. The written appointment confirms the report format, how it will be supplied and the expected reporting arrangements; no app, portal or guaranteed turnaround is implied.

  • Property, inspection date, stage, appointing client and agreed scope.
  • The observed item and a relevant criterion where it can properly be established.
  • Practical priorities, further advice and areas inaccessible or untested.
  • Agreed next steps and the scope of any separate return visit.

Incomplete work, damage, functional problems and cosmetic concerns are distinguished from maintenance and matters within an applicable tolerance. The report is not marketed by a minimum defect count. A clearly presented schedule supports discussion with the developer; it does not guarantee agreement or repair.

Illustrative schedule extract

Illustration only — not a completed HCS client report, inspection result or official PCI checklist.

Example of how an observation and its limits can be recorded
Item / locationObservation and evidenceNext step / limitation
01 / bedroom doorIllustrative item: door catches during ordinary operation. Record its position and link the relevant photograph.Ask the developer to review the fitting. No conclusion about concealed fixings or fire performance.
02 / agreed return visitIllustrative status: visible finish appears rectified; concealed repair inaccessible.Record the remaining limitation and any documents or specialist evidence required.

From enquiry to inspection and reporting

  1. Send a short brief. Identify who is appointing, the actual plot/unit, property type, stage, known dates and access position.
  2. Agree the appointment. HCS reviews suitability, scope, inspector requirements, reporting arrangements and availability. The written quotation sets the fee, VAT, reliance and any access or cancellation terms.
  3. Arrange access. Confirm readiness, safe access, utilities needed for agreed checks and the person providing entry. Discuss refused or uncertain access before an attendance is booked.
  4. Inspect and report. Record observations, photographs, priorities and limitations. The appointment states any included discussion or developer correspondence.
  5. Revisit only by agreement. Agree the original schedule and items, fee and access. Distinguish unresolved, apparently rectified, inaccessible and newly identified matters. A changed finish alone does not certify a concealed repair.

The applicable Code and pre-completion checklist

The New Homes Quality Code does not cover every purchase. Check the developer’s active registration, reservation date and purchase arrangement. Version 2 applies to relevant reservations from 2 March 2026; earlier reservations may use Version 1. Shared ownership, affordable housing and rental/investment purchases fall outside this particular Code; check other protections separately. An HCS inspection may still be appropriate when the Code does not apply.

For eligible Version 2 purchases, the pre-completion inspection takes place after notice to complete and before completion, or earlier by agreement. Use the applicable house or apartment PCI checklist. Before a qualifying appointment is confirmed, the actual inspector’s relevant professional membership, residential experience, competence and insurance must be checked. Firm regulation alone does not establish that an individual appointment meets every requirement.

The applicable Code provides an inspection opportunity; it is not a universal right for every transaction. Readiness and access still need coordinating. Website summaries do not replace the required checklist. A recorded snag does not by itself authorise delaying completion or withholding money; take transaction-specific advice from your conveyancer.

Read NHQB’s current inspection provisions and check whether your purchase is covered.

Warranties, tolerances and redress

The sale contract, developer aftercare, warranty policy, inspection evidence and complaint route do different jobs. For NHBC Buildmark, the builder warranty period is usually two years from the policy-certificate start date. Later insurance concerns defined damage in specified parts of the home and has conditions; it is not ten years of cover for every snag.

Check your provider, policy certificate, start date, notification requirements and previous correspondence. The inspection creates a dated record of observed matters; it does not automatically create or preserve a claim, transfer liability, guarantee repair or require a developer to accept every item. Warranty protection does not replace technical or conveyancing advice.

Specifications and tolerances must be appropriate to the project and warranty arrangements. Select the relevant standards edition from those records, not simply the inspection date or newest edition. NHBC requirements are not a universal statutory test. Your report should identify the relevant criterion where it can properly be established. Draft RICS material is not an operative snagging standard.

NHBC explains the builder warranty period; its later insurance cover has a different scope.

Fees and separately agreed work

Request a fixed snagging-survey quote

The written quotation confirms the property, inspection stage, accessible areas, reporting arrangements, fee and VAT before instruction.

Return visits, developer correspondence, specialist testing and additional technology are included only where expressly agreed in the written quotation. Larger homes, conversions and multiple units are scoped individually.

Before-completion and after-handover appointments can require different arrangements; the quotation confirms the actual scope. No fee difference, expedited package or included return visit is assumed. Ask for the VAT-inclusive total and a clear fee/VAT breakdown in your written quotation. No payment is taken by the enquiry form.

The professional and the appointment

Hampstead Building Consultancy Limited is listed as an RICS-regulated firm, number 923064. The written appointment identifies the responsible inspector and confirms relevant competence and insurance for the agreed service. A snagging appointment has its own agreed scope, separate from a RICS Level 2 or Level 3 home survey.

Tell us whether the client is a buyer, owner, landlord, developer or agent, and who needs to rely on the report. Scope and conflicts are considered before acceptance. See our conflicts policy; any contractor works are separately appointed.

Ongoing construction monitoring, contract administration, expert evidence, specialist investigation and claims representation require separate appointments.

Useful questions

What address details should I send for Ripley?

Use the development name and plot or unit number as well as the street address and postcode. A sales plot number may differ from the postal address. Send the site plan if that is the clearest way to identify the home and entrance.

When should I enquire?

As soon as the likely stage and dates are known. HCS checks readiness, access, scope and availability before confirming attendance or reporting timing. You can enquire without a confirmed completion date.

What if the developer has not confirmed access?

Select the actual access position in the form. Identify the relevant scheme and ask the developer for arrangements. Eligible Code cases have an inspection opportunity; other purchases need their own arrangements. Do not assume an attendance is booked or that an access right applies to every purchase.

Does an apartment inspection cover the whole building?

No. The appointment identifies the private unit and any expressly agreed accessible common areas. It does not imply access to risers, plant or lift equipment, or a whole-block fire-stopping or external-wall assessment.

What is the fee and is a return visit included?

Request a fixed snagging-survey quote. The written quotation confirms the property, inspection stage, accessible areas, reporting arrangements, fee and VAT before instruction. Return visits, developer correspondence, specialist testing and additional technology are included only where expressly agreed in the written quotation. Larger homes, conversions and multiple units are scoped individually.

Can you inspect a newly completed conversion?

Describe the new work and retained older fabric. The agreed snagging scope may address the completed work, while retained roofs, walls or concealed changes may need a separate condition survey or defect investigation.

Will the report make the developer fix every item?

No. It provides a clear record of observations and limitations for discussion. Contract terms, applicable criteria, warranty conditions and complaint processes determine the next steps. Disputed findings may require further evidence or separately scoped professional or legal advice.

Do I need an inspection if I have a new-home warranty?

A warranty and an inspection serve different purposes. Check your own policy and reporting dates. An inspection does not guarantee cover, preserve a claim automatically or replace conveyancing advice.

How will the report be supplied?

The written appointment confirms the format, delivery method and expected reporting arrangements. The core output is a numbered, photographed snagging schedule. Ask about any discussion or developer liaison before instruction; neither is assumed to be unlimited.

Send your property brief

Give the information you have. We will confirm the appropriate scope after reviewing the brief.

Scheme details and previous records (optional)

These details can be discussed after your first enquiry. Leave unfamiliar questions blank.

Mention any plans, photographs or previous reports you hold. After enquiry, HCS will confirm an appropriate way to supply files. This form does not accept attachments.

We use these details to respond to your request. Read our Privacy Policy.

An acknowledgement confirms receipt of an enquiry only. It does not confirm a booking, fee, access right or warranty deadline. Attendance and reporting availability are confirmed after review.