Your contract administration appointment
Discuss the building works in De Beauvoir with HCS. The written appointment defines the contract role, deliverables, authority, fee and any separately appointed services.
- Confirm the contract documents, responsibilities and communication arrangements.
- Agree site visits and reporting, and assess changes and payment applications under the contract.
- Define completion, defects-period and final-account tasks in the appointment.
For JCT Design and Build, discuss the Employer’s Agent role. For NEC, confirm the roles required by the selected form; an ECC appointment should distinguish Project Manager and Supervisor responsibilities. Read the contract-form guide.
Inspections and communication
Agree the number and timing of visits, progress meetings and reports before instruction. Identify work that needs to be seen before it is covered, the information the contractor must provide, and who will record outstanding decisions. Periodic inspections do not amount to continuous supervision.
Variations, payments and completion
Keep proposed changes, instructions and their cost and programme assessments together. Payment applications are assessed against the executed contract and the evidence available. The appointment identifies who prepares valuations and issues certificates or notices.
Where the contract provides for retention, the employer retains the relevant money. The contract administrator assesses and certifies the amounts and release stages within the appointed role; this does not mean HCS holds the retention money. JCT explains interim valuation and retention.
Practical completion, outstanding work, making good defects and final-account steps follow the particular contract. Agree the required records and responsibilities instead of treating one certificate as evidence of every statutory approval.
Contract planning in De Beauvoir
Documented building context
Hackney’s May 2008 appraisal explains that Benyon de Beauvoir simplified an earlier layout and developed shorter terraces and semi-detached villas. It describes the unusual gabled villas built around three sides of De Beauvoir Square from 1838, followed by classical Benyon Cottages in Hertford Road and Italianate stuccoed villas in Northchurch Road. The account expressly records variation between builders’ designs across the estate.
Existing-building records for the tender
For a dwelling with a shaped gable, mark the upper rooms, roof slopes and visible rainwater outlets on the information supplied. Ask which part of the gable or roof was addressed by any previous repair. Separate decorative work at the front from work to the covering, supports or junctions behind it.
For a De Beauvoir house with an extended rear range, list the extension, infilled side space and roof alterations in date order. Identify the document set for each and note when only marketing plans are available. Link a structural drawing to the opening it actually describes rather than to the refurbishment as a whole.
De Beauvoir tender and contract decisions
A De Beauvoir Square villa, a Benyon Cottage and a Northchurch Road stuccoed house should not receive one interchangeable tender specification. Hackney's account expressly records different designs. For the actual building, locate the roof, gable, wall finish and alterations included in the work. Ask the designer to distinguish retained features from replacements and identify the required samples, protection and inspection stages. Similar estate history does not establish the current condition or consent position at a particular address.
Where a villa has been subdivided, draw the employer's accommodation within the whole building and identify common elements affected by the proposed alteration. Obtain the relevant access and permission arrangements through the client's advisers. A change to a rear opening needs its own investigation and detail; frontage conservation work should not silently absorb that structural or weatherproofing decision. Retain the finding, designer's response and JCT instruction together so the subsequent payment assessment can follow the authorised work and its measured extent.
For gable or roof repairs, define the temporary weather protection and the point at which concealed junctions can be inspected. If a contractor proposes a different material or method, record the decision under the contract before treating it as accepted. At completion, keep the repair location, approved sample, photographs and outstanding items together. A general statement that a villa was restored cannot demonstrate that every component in the current schedule was completed, and a building contract does not itself authorise work to neighbouring or excluded accommodation.
Appointment
HCS cannot act as independent contract administrator where HCS is the contractor.
Local Sources Checked
- Hackney: De Beauvoir Conservation Area Appraisal, May 2008, Part 1 — Part 1 PDF / printed page 16, historical development: revised Benyon layout, square villas, Benyon Cottages and Northchurch Road. Cover and footer record May 2008.
Who is responsible for the appointment?
Savas Bulduk BSc (Hons) MRICS, Director & Chartered Building Surveyor. Read the professional profile and check the firm’s RICS regulation. The written proposal confirms the person responsible for your instruction and the agreed scope.
Fees and information for a proposal
Contract administration is quoted to the project; the fee reflects the contract, the value and the level of involvement required. The number of visits, valuation stages, programme and completion work affect the proposal. See the fee factors.
Send the project address, proposed works, current stage, estimated construction value and any existing or proposed contract. Include the intended programme and available drawings or specification. If the contract form is undecided, say so; value alone does not determine the appropriate form.
De Beauvoir contract administration questions
Can the same repair schedule cover a villa and a Benyon Cottage?
Identify the actual roof, gable, wall finish and alteration at each building. Specify retained features, replacements and samples individually; their shared estate history does not make their repair requirements interchangeable.
How should rear-opening work be separated from frontage restoration?
Give the opening its own investigation, design and weatherproofing detail. Retain the findings with the authorised instruction so the frontage package does not silently absorb a different structural alteration.